The Permitting Process
Are you looking to start a business in the County? Or build a garage, an addition to your property, or even a whole new house? Then you'll need a permit or two!
What do you need? What are the steps?
Please Note
Issuance of a Development Permit does not excuse the applicant from satisfying all other applicable, municipal, provincial and/or federal requirements. It is the Applicant/Registered Owner's responsibility to ensure any further permits are obtained prior to construction (building and safety codes permits are typically required for ALL development permits). If construction is commenced prior to obtaining building and safety codes permits, penalties will be applied.
Application Submitted
- Per section 683.1(1) of the MGA, “a development authority must, within 20 days after the receipt of an application for a development permit, determine whether the application is complete.” This time period may be extended by an agreement in writing between the applicant and the development authority. If the development authority does not make a determination referred to in section 683.1(1) within the time required, then the application is deemed to be complete.
- If the application is deemed incomplete by the development authority, the applicant must provide the additional information requested by the development authority by the date outlined by the development authority. If the applicant fails to submit all the outstanding information and documents on or before the date outlined by the development authority, the application is deemed refused.
- Once an application is deemed complete, turnaround on a decision can be as little as 24 hours to multiple weeks (depending on whether it is permitted/discretionary use and the complexity of the development).
Under Review
- If your application is deemed complete, the development authority reviews your application against the Land Use Bylaw, Municipal Development Plan Bylaw, and other applicable statutory documents.
- Your proposed development may be circulated to other County departments or other third parties.
- If your development is considered discretionary use, a notice of the proposed development may be circulated to adjacent landowners of the development site with an opportunity to provide comments to the development authority prior to a decision being made.
Decision
- Per section 684(1) of the MGA, the development authority must make a decision on the application for a development permit within 40 days after an application is deemed to be complete (this time period may be extended by an agreement in writing between the applicant and the development authority).
- If your development is considered discretionary use, notice of the approval will be advertised in the Beaver County Chronicle.
- If your development is considered permitted use, no notice of approval will be advertised.
Appeals
- If you are the applicant and you disagree with the decision or any conditions attached to the decision, you may file an appeal within 21 days after the date on which the written decision is given. Any person affected by an order, decision, or development permit made or issued by a development authority may appeal the decision within 21 days after the date on which the notice of the issuance of the permit was given in accordance with the Land Use Bylaw (appeal deadlines are always included in the Beaver County Chronicle notices).
- If your development is considered permitted use, no appeal can be made by the applicant unless the provisions of the Land Use Bylaw were relaxed, varied, or misinterpreted.
NOTES:
Issuance of a development permit does not excuse the applicant from satisfying all other applicable municipal, provincial and/or federal requirements. In the interest of public safety and as required by the Safety Codes Act construction permits must be covered by the appropriate permits prior to commencement of construction (Building, Electrical, Gas, Plumbing, and Private Sewage). For more information regarding how to obtain the required permits, contact The Inspections Group at 780-454-5048 or questions@inspectionsgroup.com. You must obtain the appropriate permits prior to the start of construction. Fees will be doubled if you fail to do so.
If you have any questions regarding submitting a development permit application, please contact Municipal Planning Solutions at 780-486-1991 or via our contact form.
Note - Effective October 1, 2024: Council has approved an increase in fees for:
- Permitted Use = $100
- Discretionary Use (for value up to $1 million) = $250
- Discretionary Use (for value over $1 million) = $400
- Variances = additional 50% of application fee
---
- Development Permit Application (see note above)
- Development Permit Application Fillable (see note above )
- AB Roadside Development Permit - required for development within 300 metres of the highway boundary or within 800 metres of the centre point of an intersection of the provincial highway with another County road. Permit applications can be submitted online using the Government of Alberta’s Roadside Planning Application Tracking Hub.
NOTE: Identifying wetlands is one important step in the development permit application review process. Applicants should review the Landowner Guide to the Alberta Wetland Policy to determine if any wetlands exist on their property and note their location on their site plan. Failure to identify wetlands may delay processing the application.
Once a development permit is issued, you will require Safety Codes Permits prior to the start of any building project. Safety Codes Permits are required to ensure the building or structure is in compliance with the National Building Code and related Provincial Safety Codes. NOTE: Some farm buildings may be exempt from safety codes building permits in accordance with Part 1 (Compliance), Section 1.1. of the National Building Code.
Beaver County's Safety Codes Permits are administered by The Inspections Group Inc. Applications can be found below or on their website: www.inspectionsgroup.com
Completed Safety Codes Permit Applications and payments can be submitted directly to Inspections Group. If you have any questions, please call their office at 780-454-5048 or email at questions@inspectionsgroup.com Please Note: If construction is commenced prior to obtaining the required permits, penalties will be applied
Application Forms:
- Permit Application
- Permit Application Fillable
- AB Sign Installation Permit - required for signs within 300 metres of the highway boundary or within 800 metres of the centre point of an intersection of the provincial highway with another County road. Permit applications can be submitted online using the Government of Alberta’s Roadside Planning Application Tracking Hub.
- What is a development in Beaver County?
- When do I need a development permit?
- Do I need a permit for landscaping?
- Who can apply for these permits?
- What is the difference between a permitted and discretionary use?
- What type of plans do we need to apply for a Development Permit?
- How long does it take to get a Development Permit?
- Once I have a Development Permit, how long is it valid?
- How close to the property lines can we build?
- What if my development is refused or I do not agree with the conditions attached to my development permit?
- Is there a minimum house size?
- How much will property taxes be for a new house?
- Do we need a Permit to build a deck?
- Do we need a Permit for a fence?
- Do we need permits for farm buildings, such as barns or shops?
- Are we allowed to build a second dwelling on our property?
- Who do we contact to obtain approval for an access approach to our property?
- We are selling our property and have been asked for a Compliance Certificate. What is it?
- What is my municipal address?
- What happens if there is a restricted covenant, easement or caveat on my property?
- Are permits required for renewable energy?
Q. What is a development in Beaver County?
A. Development in Beaver County is regulated by Land Use Bylaw 98-801, as amended. Most development requires a development permit and is defined in the Bylaw as follows:
(a) an excavation or stockpile and the creation of either of them, or
(b) a building or an addition to, or replacement or repair of a building and the construction or placing of any of them in, on, over or under land, or
(c) a change of use of land or a building or an act done in relation to land or a building that results in or is likely to result in a change in the use of the land or building, or
(d) a change in the intensity of use of land or a building or an act done in relation to land or a building that results in or is likely to result in a change in the intensity of use of the land or building.
The definition also includes the demolition or removal of a building or the placement of an already constructed or partially constructed building on a lot.
Q. When do I need a development permit?
A. Most development in Beaver County requires a development permit. The following development does not require a development permit, although other permits under the Alberta Safety Codes Act or other legislation or regulations may be required:
(a) The carrying out of works of maintenance or repair to any building, provided that such works do not include structural alterations or major works of renovation, including:
i) minor utilities, the definition of which shall be as determined at the sole discretion
of the Development Authority;
ii) private driveways and patios accessory to a dwelling;
iii) an unenclosed deck or a deck enclosed by a rail or parapet wall, with a floor less than 1 m (3.3 ft.) in elevation above grade;
iv) landscaping where the existing grade and surface drainage pattern
is not materially altered;
(b) The completion of a building which was lawfully under construction at the date of the approval of the Bylaw, provided that the building is completed in accordance with the terms of any permit granted in respect of it and subject to the conditions to which the permit was granted and provided also that the building, whether or not a permit was granted in respect of it, is completed within a period of twelve months from the said date of the approval;
(c) The use of any such buildings allowed under Section 1.4(b) of the Bylaw;
(d) The erection or construction of gates, fences, or walls or other means of enclosure and the maintenance, improvement and other alterations of any such gates, fences, or walls, except as follows:
i) In the Agricultural District, no gates, fences, or walls or other means of enclosure will be allowed where such gates, fences, or walls abut on a road or a highway used by vehicular traffic within the setback area shown in Figures 9.2 - 9.6;
ii) In the Country Residential District, a Development Permit will be required for gates, fences, or walls or other means of enclosure on corner lots or where abutting on a road or a highway used by vehicular traffic, and for gates, fences, or walls greater than 1.84 metres (6 feet) in height in front, rear, or side yards;
iii) In the Urban General District, a Development Permit will be required for gates, fences, or walls or other means of enclosure on corner lots or where abutting on a road or a highway used by vehicular traffic, and for gates, fences, or walls greater than 0.92 metres (3 feet) in height in front yards and greater than 1.84 metres (6 feet) in rear or side yards;
(e) A temporary building, the sole purpose of which is incidental to the erection or alteration of a building for which a permit has been issued under this Bylaw, and which is not a dwelling or used as a dwelling;
(f) The maintenance and repair of public works, services and utilities carried out by or on behalf of federal, provincial and municipal public authorities on land which is publicly owned or controlled;
(g) The erection or construction of fencing for extensive agricultural uses;
(h) The development of land for extensive agricultural purposes, excepting for:
i) a dwelling;
ii) a garage;
iii) permanent farm buildings and dugouts located within 38.0 m (125 ft.) of the centreline of a rural County road, or within 63.7 m (209 ft.) of the centreline of a secondary road, or within 71.6 m (235 ft.) of the centreline of a primary highway;
(i) The development of land for a confined feeding operation or a manure storage facility within the meaning of the Agricultural Operation Practices Act if the confined feeding operation or the manure storage facility is the subject of an approval, registration or authorization under Part 2 of that Act.
(j) The demolition or removal of a building or improvement.
(k) Change of hours of operation of any permitted use development in the Landfill and Composting District for which a development permit has been issued.
(l) Change of sequence of development of cells within a landfill for which a development permit has been issued.
For more information, contact Municipal Planning Solutions, at 780-486-1991
Q. Do I need a permit for landscaping?
A. No permit is required for landscaping where the existing grade and surface drainage pattern is not materially altered. However, for landscaping where the existing grade and surface drainage pattern is materially altered, a permit will be required to show the proposed grading plan. The grading plan must show the re-established drainage course for the property. Drainage should not interfere with adjacent properties, roadways, and/or environmental features
Q. Who can apply for these permits?
A. The registered owner(s) of the land or an authorized person acting on the landowner(s) behalf may apply for a Development Permit. Most of the time, the landowner applies for the Development Permit and Building Permits, and the specific trades apply for the Electrical, Gas, Plumbing and Private Sewage Disposal Permits.
Q. What is the difference between a permitted and discretionary use?
There are two types of uses in every district: permitted and discretionary. Permitted uses are approved by the Development Authority upon meeting the regulations in the Land Use Bylaw. Decisions cannot be appealed unless the provisions of the land use bylaw were relaxed, varied, or misinterpreted. Discretionary uses are assessed and approved on a case by case basis based on the compatibility and impact of the proposed development with adjacent developments and the surrounding area. Discretionary permits may be referred to adjacent landowners and various agencies for comments. Once a decision is made, the permit will advertised for two consecutive weeks in the Beaver County Chronicle. Following that, there will be a fourteen (14) day appeal period. Compliance with the County Municipal Development Plan and Land Use Bylaws are required for all development and uses.
Q. What type of plans do we need to apply for a Development Permit?
A. The County requires a site plan of your proposed development indicating distances from property lines, dimensions of building, driveway/access, and distance from the driveway to the quarter section line (for addressing purposes), distance from water lines, power lines, wells, septic, and wetlands (if present). A copy of the floor plan or blueprints will also be required, if applicable.
Q. How long does it take to get a Development Permit?
A. Processing times for a development application vary depending on the type of development. The Development Authority must make a decision on an application within 40 days of receipt of the completed application. If all required information is submitted with the application, a decision may be granted much sooner (5-10 business days). Discretionary use permits usually take 4-6 weeks due to extra processing requirements.
Please note that obtaining a development permit does not relieve the permit holder from complying with:
- The requirements of the Alberta Safety Codes Act.
- The requirements of any other appropriate federal, provincial or municipal legislation.
- The conditions of any caveat, covenant, easement or other instrument affecting a building or land.
Q. Once I have a Development Permit, how long is it valid?
A. If the development authorized by a permit is not commenced within twelve (12) months from the date of its issue, the permit is deemed void, unless an extension to this period has been granted by the Development Authority prior to the expiry date.
Q. How close to the property lines can we build?
A. The setbacks to the property lines vary depending on the land use district in which the property is located and the type of road that is adjacent. Contact the Planning & Development Department to get exact information on the setback requirements in your particular land use district.
Q. What if my development is refused or I do not agree with the conditions attached to my development permit?
A. A condition attached to a development permit or a refusal may be appealed to either a local or Provincial appeal board (dependent on type of application). You or your authorized agent may appeal by sending a written notice, stating reasons, and the $200 appeal fee (if applicable) within 21 days of the date of decision to the Development Authority. Click on How to Appeal Planning Decision for more information.
Q. Is there a minimum house size?
A. Yes, Beaver County restricts the minimum size of a house in the Country Residential District and the Urban General District to 74.3 m² (800 ft²); or in the case of a split level or bi-level, the first floor above ground level must be a minimum of 55.7 m² (600 ft²). In the case of mobile homes, additions are not included in the calculation of the minimum floor area. The developer may also have a restriction on house sizes and this would be identified in a caveat registered against the property. In the Agricultural District, there is no restriction on house size.
Q. How much will property taxes be for a new house?
A. Property taxes vary depending on the values of the property and house. For more information on property taxes, please contact the County's Assessment Department at (780) 663-3730.
Q. Do we need a Permit to build a deck?
You do not need a Permit for an unenclosed deck that is less than 1.0 m (3.3 ft.) in elevation above grade.
Q. Do we need a Permit for a fence?
No permit is required for the construction of gates, fences, or walls or other means of enclosure and the maintenance, improvement and other alterations of any such gates, fences, or walls, except as follows:
i) In the Agricultural District, no gates, fences, or walls or other means of enclosure will be allowed where such gates, fences, or walls abut on a road or a highway used by vehicular traffic within the setback area shown in Figures 9.2 - 9.6;
ii) In the Country Residential District, a Development Permit will be required for gates, fences, or walls or other means of enclosure on corner lots or where abutting on a road or a highway used by vehicular traffic, and for gates, fences, or walls greater than 1.84 metres (6 feet) in height in front, rear, or side yards;
iii) In the Urban General District, a Development Permit will be required for gates, fences, or walls or other means of enclosure on corner lots or where abutting on a road or a highway used by vehicular traffic, and for gates, fences, or walls greater than 0.92 metres (3 feet) in height in front yards and greater than 1.84 metres (6 feet) in rear or side yards;
Q. Do we need permits for farm buildings, such as barns or shops?
A. Depending on the location of your property, a Development Permit may be required. If you are in the Agricultural District, development for extensive agricultural purposes does not require a Development Permit unless located within setback restrictions. If you are in the Country Residential District, you must obtain a Development Permit. Farm buildings on agricultural zoned land for agricultural use, may be exempt from the National Building Code. However, private residence buildings (Dwellings and accessory buildings that serve the dwelling) are NOT exempt and development permits ARE required..
Q. Are we allowed to build a second dwelling on our property?
A. A second or additional dwelling is a discretionary use in most districts. A development permit is required and will be assessed on an individual basis.
Q. Who do we contact to obtain approval for an access approach to our property?
A. The Public Works Department can assist in the process for obtaining approval for accesses to rural properties. They can be reached at (780) 663-3730.
Q. We are selling our property and have been asked for a Compliance Certificate. What is it?
A. Prior to approving a mortgage, many financial institutions now require a compliance certificate to ensure that the property complies with municipal bylaws. A Real Property Report, prepared by a qualified surveyor, is reviewed by the Development Officer to ensure that improvements on the property have valid Development Permits, and comply with the zoning, floor area, and setback requirements of the Land Use Bylaw. Compliance with Safety Codes regulations is not covered by Beaver County’s Letter of Compliance. Click here for more information.
Q. What is my municipal address?
A. Call the Beaver County Service Centre if you don’t know your municipal address. Bylaw No. 00-816 requires that every occupied parcel of land has its municipal address displayed; and that every person who obtains a Development Permit for the construction of a commercial, residential, or industrial development erect an address sign within three months.
For more information, contact Planning and Development via our contact form, or call 780-486-1991.
Q. What happens if there is a restricted covenant, easement, or caveat on my property?
A. Check that your proposed development, building, or structure will not conflict with any restrictive covenant, easement, or caveat registered against the title to the subject lands. Before any action is taken we advise you to search your land title to determine if a restrictive covenant, easement or caveat is registered against the land. Be advised that a landowner or stakeholder with an interest in the restrictive covenant, easement, or caveat registered against your title is entitled to take legal action against you should you violate or fail to comply with the requirements of the covenant, easement, or caveat.
Q. Are permits required for renewable energy?
A. Generating energy from renewable resources is becoming increasingly important and needs to be fully considered with the rise in conventional energy prices and population growth. Changes have been made to the County’s Land Use Bylaw to make it as efficient as possible to install renewable and alternate energy systems.
Click here for regulations regarding Solar Collector development.
Click here for information regarding the County's Eco-Friendly Industrial District.
Click here to download the Renewable Energy handout.
Solar Collector means a device or combination of devices used to collect solar energy. The solar energy is absorbed and then converted into thermal or electrical energy. The different types of solar collector systems can be mounted to the roof, wall, or ground.
Solar Farm means a large number of solar collectors set up to collect solar energy with a total combined area of 0.40 ha (1.0 ac) or more. These are stand-alone assemblies mounted on racking on the ground.
Renewable and Alternate Energy Facility means a building or development that generates energy using natural or renewable resources (e.g. wind, geothermal, bio-fuels) or generates energy using a process that reduces the amount of harmful emissions to the environment. Examples include district heating and cogeneration.
Permit Requirements
No development permit is required for solar collectors that are installed primarily for private or on-site use (although contribution to the grid may be possible). These include panels mounted to the roof, wall, and ground (with a floor area of 10m2 or less). For all other uses, a permit is required. Any development regulations (e.g. setbacks) will apply to all land uses regardless of permit requirements.
Approvals may be required from a provincial or federal agency prior to the operation of any renewable energy system. These may include approvals from Alberta Utilities Commission (AUC), Safety Codes (e.g. electrical permit) and your utility service provider (e.g. Fortis Alberta).
In addition, under Section 619 of the Municipal Government Act, any license, permit, or approval granted by AUC will prevail over any development decisions made by the County. Moreover, a permit issued by the County is only for compliance with the use, size and setback regulations. The actual design and operation of these systems are regulated provincially, and beyond the control of the County.
Other Resources
Solar Energy Society of Alberta
Fortis Alberta Micro-Generation
Alberta Water Wells - Find water wells on your property