Construction Schedule - June 26
2024 Construction Schedule
|
|||
Task |
Start Date |
End Date |
Update - June 19 |
Culvert Maintenance |
Apr 1 |
Nov 1 |
Ongoing |
Patching oil roads throughout the season |
May 1 |
Sep 29 |
Ongoing |
Terra-Cem |
|||
Twp 490 between Rge rd 124 & Rge rd 120 |
May 13 |
May 31 |
|
Phase 1 (Cement) |
Phase 1 - Complete |
||
Rge rd 120 between Twp 490 & just north of colony entrance. |
May 28 |
May 31 |
|
Phase 1 (Cement) |
Phase 1 - |
||
Holden streets. |
Jul 2 |
Jul 4 |
|
Phase 1 (Cement) |
Phase 1 - |
||
Rge rd 161A between Hwy 14 & Hwy 855 |
Jul 5 |
Jul 9 |
|
Phase 1 (Cement) |
Phase 1 - |
||
Rge rd 200 between Hwy 630 & Park entrance |
Jul 11 |
Jul 21 |
|
Phase 1 (Cement) |
Phase 1 - |
||
Rge rd 202 between Twp 502 & Twp 504 |
Jul 30 |
Aug 8 |
|
Phase 1 (Cement) |
Phase 1 - |
||
Rechip 2 miles TBD (Contracted for late summer) |
Aug 12 |
Aug 23 |
|
Shoulder Pulls |
Aug 1 |
Oct 2 |
|
Shoulder pull Rge rd 202 between Twp 502 & Twp 504. |
Jul 24 |
Jul 29 |
|
Backsloping (location TBD) |
Oct 2 |
Nov 1 |
|
Gravelling |
Mar 13 |
Dec 22 |
Ongoing |
Dust Control- 1st Application |
May 1 |
May 19 |
Complete |
Dust Control- 2nd Application |
Aug 8 |
Aug 15 |
|